Electrified Double Track Project. Ipoh-Padang Besar
Fact Find
View track alignment.  Site Map.
 
About Elelctrified Double Track Project
 

The northern Electrified Double Track project Ipoh to Padang Besar comprises the design and construction of the infrastructure and systems works for 329-km. Work involves the laying of two new parallel tracks to replace the existing single-track, including new stations, bridges, as well as modern electrification and signalling systems.

Background
July 2006
Government reactivated the Electrified Double Track project since deferment in December 2003

March 2007
MMC-Gamuda Joint Venture submitted Technical and Financial Proposals to the Government

Oct 2007
The negotiations led by the Economic Planning Unit were concluded

13 December 2007
Letter of Acceptance was issued to MMC-Gamuda Joint Venture

Scope of Work
Route: Overall Length – 329 Km
Sector 1: Kedah Line – 158 Km Bukit Mertajam–Padang Besar
Sector 2: Mainline – 171 Km (Butterworth – Ipoh)
Station:
Major – 7
Minor – 14
Halt – 10
Depot – 3
 
State Major Minor Halt Total
Perlis 2 1 - 3
Kedah 1 4 3 8
P.Pinang 2 3 3 8
Perak 2 6 4 12
Tunnel: Bukit Berapit – 3.3km (Perak)
Larut – 0.33km (Perak)
Depot: Padang Besar (Perlis), Prai (P.Pinang) and Bukit
Mertajam (P.Pinang)
Bridges:

Road Over Bridge (ROB) – 66 No
Road Under Bridge (RUB) - 8 No
River Bridge (RB) – 75 No
Motorcycle/ Pedestrian Bridge – 45 No

State ROB RUB RB PMB Total
Perlis 5 0 6 5 16
Kedah 21 4 31 16 72
P.Pinang 19 0 11 29 38
Perak 21 4 27 16 68
Special Structure: Prai Swing Bridge – 282 m
Marine Viaduct (Bukit Merah) – 3.5km
KTMB Quarters: 220 Units
Systems: Electrification
Signaling & Control
Communication

 

 